Cantwell was engaged in to design, supply, construct, test, and commission water booster pumping stations for a Data Centre client.
Data Centre Project Machinery

Location: Ireland

Commencement Date: 2020

Project Objective: Cantwell was engaged to design, supply, construct, test, and commission 2 water booster pumping stations, boosting water from the existing mains supply to the site.

The primary function of the pumping station was to boost water pressure from the mains water supply to the Data Centre.

Project Solutions: Both pumping systems were designed and built as walk-in skids housed in GRP Kiosks.

The main components of the skids included:

 

  • GRP Housing c/w Steel Base
  • Grundfos Hydro MPCE Booster Set
  • Stainless Steel Suction & Discharge Pipework
  • Associated Instrumentation
  • Lifting Gantry included
  • Full Electrical Installation
  • Heating & Ventilation
  • ATyS Transfer Switch

 

The complete system was constructed and tested off site, removing time spent at location and adhering to Covid 19 health and safety protocol.

As standard with Cantwell, work was completed timely, cost effectively and fully operational as promised to serve the purpose required and to the satisfaction of our client.