Location: Ireland
Commencement Date: 2020
Project Objective: Cantwell was engaged to design, supply, construct, test, and commission 2 water booster pumping stations, boosting water from the existing mains supply to the site.
The primary function of the pumping station was to boost water pressure from the mains water supply to the Data Centre.
Project Solutions: Both pumping systems were designed and built as walk-in skids housed in GRP Kiosks.
The main components of the skids included:
The complete system was constructed and tested off site, removing time spent at location and adhering to Covid 19 health and safety protocol.
As standard with Cantwell, work was completed timely, cost effectively and fully operational as promised to serve the purpose required and to the satisfaction of our client.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |